4h ago
Bitdeer starts building a 100 MW Alberta compute site with an on-site gas plant
Bitdeer (NASDAQ: BTDR) said Tuesday it began construction near Fox Creek, Alberta, on a combined power-and-data-center project designed for roughly 100 MW of computing. The plan pairs a 101 megawatt natural gas plant with a data center, represents a $155 million investment (about C$214 million), and is expected to be energized in the second quarter of 2027.